Soufriere/Scott's Head Sea Defences and Road Improvement

Soufriere/Scott's Head Sea Defences and Road Improvement

Soufriere/Scott's Head Sea Defences and Road Improvement (2010) - Phase 2
Contractor Offshore Civil and Marine Inc.
Total Project Cost EC$15,987,271
Revised EC$18,637,271
(Variation of EC$2.65M approved for project completion)
Funding Source Venezuela (ALBA)
Project Objective Construction of a sea defence wall and associated road works between the village of Soufriere and Scotts Head. In addition, the rehabilitation of damaged section of walls and affected roads in Scotts Head village.

Date

28 January 2023

Tags

Sea Defence

Our Mission

To develop resilient physical infrastructure and provide digital services the can withstand and/ or recover quickly from adverse events through improved; standards, institutional systems, and regulatory oversight.

Our Vision

Resilient infrastructure, integrated technology

Extra links

Contact Details

Address:1st Floor,
Government Headquarters,
Kennedy Avenue, Roseau,
Commonwealth of Dominica

Call Us : + 1 (767) 266 3524
Mail Us : publicworks@dominica.gov.dm